Tower Crane Dismantling Method Statement -

At a critical height—usually when the tower crane’s remaining top is 15–20 meters above the roof—the method statement triggers a handover. The tower crane is now too short to lift its own mast sections without the jib striking the building.

Now the mobile crane takes command.

This phase is the highest risk: two cranes interact within metres of each other. The method statement mandates an exclusion zone and a single signalman with absolute authority. tower crane dismantling method statement

Project: [Project Name]
Location: [Site Address]
Crane Details: [Make, Model, Serial No., Max Capacity, Jib Length, Height under Hook, Mast sections]
Date of Dismantling: [Planned Date(s)]
Prepared by: [Name, Role]
Approved by: [Site Manager / Project Director]


| Condition | Action | |-----------|--------| | Wind speed > 20 mph (9 m/s) | Stop all lifts above 50ft height. | | Wind speed > 25 mph (11 m/s) | Complete stop – secure partial load. | | Rain / fog (visibility < 50m) | Stop work. | | Lightning within 10 miles | Stop work, evacuate crane area. | | Night work | Only permitted with full lighting (500 lux minimum). | At a critical height—usually when the tower crane’s


Using the auxiliary mobile crane.

Critical: Never stand under the jib during pin removal. Use tag lines. This phase is the highest risk: two cranes

This method statement covers the safe dismantling of a [Insert Crane Model] tower crane from a [Insert Site Address] construction site. The objective is to reduce the crane to manageable components using a mobile assist crane (or climbing crane/jib crane method) with zero incidents.

Before any bolt is loosened or section lifted, a thorough pre-dismantling audit must be completed and documented.

For practical use, a tower crane dismantling method statement should include this table format on the first page:

| Project Name: | XYZ High-Rise | |------------------|----------------| | Crane Model: | Potain MD 560 | | Dismantling Date: | 15 Nov 2025 | | Appointed Person: | J. Smith | | Mobile Crane: | Liebherr LTM 1160 (160t) | | Weather Limit: | Wind < 20 mph, no precip | | Sequence Step | Responsible | PPE | Permit Required | | 1. Site setup | Supervisor | HV, Gloves | Exclusion zone | | 2. Jib dismantle | Rigger A | Harness, radio | Lift plan | | 3. Counter-jib | Rigger B | Harness | Lift plan | | … | … | … | … | | Emergency contact: | Site security: 555-0199 ||